NEW BRIGG ALDI STORE ROADWORKS & MINI-ROUNDABOUT UPDATE
Although Aldi has yet to announce an opening date for its new Brigg store which has been under construction for several months, we now know that an important part of the project is to be undertaken during August.
Coun Rob Waltham, who is the Leader of North Lincolnshire Council, our local highway authority, told Brigg Town Council's latest meeting that the current roadworks on Bridge Street, relating to Aldi's development, must be completed by the end of this month, and added that a section of the A18 on Bridge Street will then be resurfaced in August. This work will be carried out at night to reduce inconvenience.
Coun Rob explained that details of the mini-roundabout, to be created to serve the store site, have yet to be submitted to the council for approval.